Cypress Creek Mitigation Efforts

October 7, 2026 5:47 pm
Title graphic for Harris County MUD 286 Cypress Creek Mitigation Efforts, featuring a detention basin concept plan with labeled project elements in the background.

The Harris County Flood Control District have been developing several stormwater detention basins in our community.

Flood damage reduction projects help reduce flooding risks for homes within the District, while other programs maintain our drainage investment, plan for the future, and turn stormwater detention basins and channels into community amenities and environmental assets.

TC Jester Stormwater Detention Basin

PROJECT OVERVIEW

  • A four-compartment stormwater detention basin near the intersection of TC Jester Blvd and Cypresswood Dr
  • Designed to provide approximately 1200 acre-feet ' of stormwater storage capacity-roughly 1200 football fields covered in one foot of water

Funding Sources

  • 2018 Bond Program
  • Community Development Block Grant
  • Federal Emergency Management Agency
  • Texas Water Development Board
Project Details
Map of Cypress Creek detention basin compartments showing East Compartments 1A, 1B, and 2, plus a West Compartment, near Cypresswood Drive and T.C. Jester Boulevard.

Batch 5: Cypress Creek Channel Rehabilitation and Stormwater Detention Basin

PROJECT OVERVIEW

  • Channel rehabilitation to stabilize two segments of the main stem of Cypress Creek and minimize potential erosion
  • Two stormwater detention basins are under construction to mitigate downstream impacts

Funding Sources

  • 2018 Bond Program
  • Community Development Block Grant
Project Details
Map of Cypress Creek flood mitigation projects showing channel rehabilitation near Kuykendahl Road and a stormwater detention basin and channel rehabilitation project near I-45.

Westador Stormwater Detention Basin

PROJECT OVERVIEW

  • A wet-bottom stormwater detention basin southeast of the intersection of Ella Blvd and Cypresswood Dr
  • Designed to hold approximately 207 acre-feet of stormwater-roughly 207 football fields covered in one foot of water
  • Expected to be completed in Q1 2027
Project Details
Map of the Mercer stormwater detention project showing north and south basins, wetlands, an equalizer pipe, detention outfall to Cypress Creek, and the project boundary near Hardy Road.

Mercer Stormwater Detention Basin

PROJECT OVERVIEW

  • A two-compartment stormwater detention basin near the intersection of Hardy Toll Rd and FM 1960
  • Designed to hold approximately 512 acre-feet of stormwater-roughly 512 football fields covered in one foot of water
  • Completed in Q1 2026
Project Details
Map of the Mercer stormwater detention project showing north and south basins, wetlands, an equalizer pipe, detention outfall to Cypress Creek, and the project boundary near Hardy Road.

Projects in Preliminary Engineering